Just Won a Contract? How to Mobilise Site Labour in 10 Days

Last updated: April 2026 · 7 min read · For SME contractors

You've won the contract. The client wants boots on site inside a fortnight. This is the checklist we run with SME contractors across London and the South East every week. It assumes a project up to about £2m — fit-out, refurb, residential, small groundworks — and a workforce of roughly 4–20 people.

Before day one — a 30-minute prep

  • • Confirm site address, access route, and site working hours.
  • • Nail down start date and expected duration.
  • • List trades required by phase and rough numbers.
  • • Note ticket requirements (CSCS level, SSSTS/SMSTS, asbestos awareness, first aid, plant tickets).
  • • Decide welfare, PPE, and induction arrangements.
  • • Nominate the on-site point of contact and their number.

Send this as a single brief to your agency. It saves three rounds of email and gets a shortlist back within hours.

Week 1 — Contracts, admin, workforce brief

  • Day 1 — Confirm contract, appoint site manager, kick off internal handover.
  • Day 1–2 — Send workforce brief to agency: trades, numbers, start date, site address, shift pattern, ticket requirements, welfare on site.
  • Day 2 — Issue subcontractor and plant enquiries in parallel. Book welfare unit and hoarding.
  • Day 3 — Client pre-start meeting. Lock down programme critical path.
  • Day 3–4 — RAMS in draft. Induction pack in draft. Confirm CDM roles.
  • Day 4 — Agency returns worker profiles for approval. Verify tickets on CSCS Smart Check.
  • Day 5 — Insurances and warranties sent to client. Welfare delivered to site. First week's workforce confirmed.

Week 2 — Set-up, induction, first shift

  • Day 6 — Temp power and site security in place. First delivery slots booked.
  • Day 6–7 — Site set-up: hoarding, signage, welfare fit-out, waste plan.
  • Day 7 — RAMS signed off. Induction pack finalised. Toolbox talks scheduled.
  • Day 8 — Confirm workforce start day. Send site address, arrival time, PPE requirements, and induction slot to the agency.
  • Day 8–9 — First workers arrive for induction. Right to Work verified on site as a second check.
  • Day 9 — Snag walk with site manager. Confirm labour balance for week 3.
  • Day 10 — Site live. First productive shift. Debrief with agency on any gaps, adjust week 3 numbers.

Common bottlenecks and how to dodge them

  • Welfare arriving late. Book it on day 1 — lead times slip to 5–7 days in busy months.
  • RAMS not signed off in time. Draft on day 3, get client sign-off before day 8 so workers don't stand around on day 10.
  • Right to Work delays. If your agency doesn't provide RTW evidence with the worker profile, they aren't ready to deploy.
  • Under-briefed workforce. Send the site address, arrival time, parking, and induction slot the day before. First-day no-shows are usually a briefing failure, not a worker failure.
  • One-agency risk. For anything over 15 workers, use two agencies for the same trade so a shortfall from one is covered.

What to send your agency on day 1

A one-page workforce brief that includes:

  • • Site address and postcode
  • • Client / main contractor name (if not you)
  • • Start date and expected end date
  • • Trades and numbers by week
  • • Shift pattern (7:30–4:30, weekends?)
  • • Ticket requirements per trade
  • • PPE requirements (hi-vis colour, gloves spec, safety spec glasses)
  • • Welfare and parking arrangements
  • • Site contact name and mobile
  • • Preferred payroll model (PAYE / umbrella / CIS)

Frequently Asked Questions

Just won a contract? Let's mobilise.

Send us your workforce brief. We'll come back the same day with a shortlist, rates, and a start-date plan.